Harborview Medical Offices
A three-storey outpatient clinic with imaging suites, built on a tight downtown site with a live street on two sides.
CommercialIn progress · week 24/38
DrawingPRJ-102
ProjectForgemont
Scale1:100
RevC
64′-0″ TO ROOF218′-0″ FRONTAGE
Project sheet
ClientHalden Health
LocationTacoma, WA
ContractGMP · $14.6M
Area38,000 sq ft
Storeys3 + roof plant
ArchitectLinework Studio
StartJan 06, 2026
HandoverSep 26, 2026
The brief
Halden Health needed imaging suites operational before a lease elsewhere expired. We re-sequenced the steel to close in the MRI wing first and bring the shielding trades in eight weeks early.
MRI and CT suites closed-in first for early shielding work
Night pours to keep the street open during the day
Weekly owner walk with the clinical planning team
Programme
Where the build stands
Updated every Friday by the site superintendent.
Live project · Tacoma, WA · 38,000 sq ft · 3 storeys
Harborview Medical Offices
76%
Week 24 of 38 On schedule
01
Plan
Jan 06 – Feb 14
Complete
Design development, GMP signed100%
02
Permit
Feb 17 – Apr 04
Complete
Building permit B26-0412 issued100%
03
Foundation
Apr 07 – May 23
Complete
Mat slab poured, 612 yd³100%
04
Frame
May 26 – Aug 15
In progress
Level 3 steel topped out, deck pour Thu78%
05
Finish
Aug 18 – Sep 26
Upcoming
MEP rough-in scheduled0%
Site diary
This week on site
Level 3 steel topped out; ceremonial beam signed by the Halden team.
Metal deck on level 3 inspected and approved by the city.
Roof-top unit curbs set; MEP coordination model v14 issued.
Site safety record
412
Days without a lost-time incident
Hours worked since last LTI1,284,630
Projects delivered1286since 1987
Handed over on time96.4%last 5 years
TRIR0.42industry avg 2.8
Crew safety-certified100%OSHA 30 / first aid
Gallery
Progress photos
IMG 01Crew placing rebar and formwork on the level 2 deckIMG 02Workers on scaffolding at the facadeIMG 03Engineers measuring a masonry wallIMG 04Surveyor setting out with a level
Client
Client report · 01
“Forgemont handed over our clinic eleven days early. The weekly site report meant our board never had to ask for an update.”